WASHINGTON — The U.S. Army is asking private companies to lease land at nine of its installations to build commercial power plants — and, if the Army gets its first choice, data centers beside them.
The Department of the Army issued the request for proposals, No. DACA27-1-27-0015900, on Nov. 19, and the solicitation is posted on SAM.gov, the federal contracting site. It seeks competitive proposals from private, public and nonprofit entities to lease non-excess Army land under long-term Enhanced Use Leases.
Under the leases, the winning companies would design, finance, permit, build, own, operate and eventually decommission the projects, and would have to restore the land to its prior condition before the lease expires, according to the solicitation.
Power is the requirement; the data center is the option. The Army says its preference is for projects that combine a power generation facility and a commercial data center on one campus. A company may propose a power plant alone — but proposals for a data center only “will not be considered,” the solicitation states.
For the data centers themselves, the Army’s first preference is hardened, physically isolated campuses built to ICD 705 standards for Top Secret workloads. Its second is large hyperscale facilities for artificial intelligence and high-performance computing, with a targeted power usage effectiveness of 1.15 or less. The solicitation requires the power projects to be able to restore electricity to the host installation within one hour of a grid outage and sustain it for at least 14 continuous days, and requires water use to be net-neutral or better.
The nine installations are Blue Grass Army Depot in Kentucky; Pine Bluff Arsenal in Arkansas; Tooele Army Depot in Utah; Sierra Army Depot in California; Fort McCoy in Wisconsin; Fort Bragg in North Carolina; Fort Hood in Texas; Fort Rucker in Alabama; and Joint Base Lewis-McChord in Washington.
None of the nine is in Ohio. The closest to this region is Blue Grass Army Depot, near Richmond, Kentucky. The Army’s list lands while some of the largest data center fights in the country play out in Ohio, including SB Energy’s proposed 10-gigawatt campus on and around the former Portsmouth Gaseous Diffusion Plant site in Pike County.
The Army says it will consider a range of generation and storage technologies, including natural gas turbines, fuel cells, hydrogen systems, advanced nuclear reactors, battery storage and solar paired with dispatchable generation. Site tours at the nine installations run from Nov. 30 through Dec. 17. Questions are due Jan. 6, 2027, and proposals are due by 5 p.m. Eastern on Jan. 18, 2027.
The solicitation is the Army’s third and broadest round this year under its Strategic Capital Initiative. In March, the Army conditionally selected Carlyle for a data center project on about 1,384 acres at Fort Bliss, Texas, and CyrusOne for about 1,201 acres at Dugway Proving Ground, Utah; neither lease has been finalized. The Army may award one or more leases under the new solicitation — or none.