PIKETON, Ohio — The warning is one sentence long, and it sits in the data center developer’s own permit file at the Ohio EPA.
“Any pumping of groundwater near the facility could pull the plumes off-site.”
Ohio EPA wrote that sentence on November 20, 2026, in its official comments on the 401 Water Quality Certification application for the PORTS Technology Campus — the SB Energy data center project rising on private land next to the former Portsmouth Gaseous Diffusion Plant in Pike County. The agency was talking about the contaminated groundwater plumes underneath the old federal plant next door: plumes of trichloroethylene, a chlorinated solvent, sitting in the Gallia formation, still under active treatment and remediation by the U.S. Department of Energy.
Four days later, a second letter landed. This one came from the Department of Energy itself, addressed to the developer’s sister company. The government’s air monitors and six of its groundwater monitoring wells — the instruments that tell the public what is coming off the old plant — now sit on land the developer bought. Keeping them there, DOE wrote, requires the developer’s permission. If the answer is no, the government will pull its equipment out, or abandon it in the ground.
Both letters are public records in Ohio EPA’s document portal. Here is what they say, in full, with the pages shown.
The warning
Ohio EPA’s comment 3.a, quoted word for word from the agency’s November 20 notice:
“There are several contaminated groundwater plumes of chlorinated organics (trichloroethlylene) within the Department of Energy (DOE) facility located to the west of the project area that are undergoing active treatment and remediation. The plumes are within the Gallia formation. Any pumping of groundwater near the facility could pull the plumes off-site. The Scioto Valley aquifer, located to the west of the DOE facility, is where DOE sources most of their water.”
The agency then demanded to know where the data center’s water would come from, and said that if the project planned wells or surface-water intakes, Ohio EPA’s drinking-water division would have to be consulted for applications and approvals.

In plain terms: the groundwater under the old plant is contaminated, pumps are the one thing that can move that contamination, and the state wanted it in writing that the data center would not become the thing that drags the plumes toward people’s wells.
The answer on water: no wells — the water comes from DOE itself
Portsmouth DevCo, LLC answered on November 23, 2026, through its consultant Stantec. The project, the company said, will not drill its own groundwater wells. Its water supply will be purchased drinking water from the Department of Energy’s own water treatment plant, delivered through a new line. The line, the company said, “is being planned in close coordination with DOE to avoid known contaminated areas and areas undergoing remediation or excavation.” DOE’s plant draws from the Scioto Well Field along the Scioto River. Construction water will come through DOE-authorized supply points, and the company said DOE and Ohio EPA have reviewed the proposed fill-station locations and agreed on their safety and feasibility.
So the data center’s water plan runs through the same federal plant whose plumes prompted the warning — with the pipe routed, on paper, around the contamination.
The soil question
Ohio EPA’s second comment, 3.b, records what the public has been saying in the project’s permit proceedings:
“Many commenters expressed concerns over legacy contamination in soils, surface water, and ground water due to the proximity of the DOE facility. Please provide a demonstration that the excavated soil and fill material will be clean and free of contaminated materials, such as heavy metals, VOC, and PCBs.”
The company’s answer: the campus sits on private property outside the DOE fence, it does not plan to use soil or fill from the former plant, and it tested the ground. Two testing programs, both paid for by the developer, are now in the public file.
The Stantec study (April 10, 2026). Stantec sampled surface soil at 15 locations on the land SB Energy is evaluating, at the spots nearest the plant and downwind of it, taking samples two to three inches and five to six inches down. The samples went to Eberline Analytical in Oak Ridge, Tennessee, and were tested for uranium only — U-234, U-235 and U-238. U-234 and U-238 came back below Ohio’s background averages everywhere. Nine samples showed U-235 above the background average, which Stantec ruled “indistinguishable from background” once laboratory uncertainty is counted. Its conclusion: uranium in the surface soil is not statistically different from natural background, and windblown dust from the old plant “does not appear to have affected surface soil quality.”

The QAL-TEK study (August 16, 2026). The bigger report — 59 pages — covered three efforts. Phase 1 tested the property the report itself identifies as the Oklo property, immediately east of the plant’s reservation boundary. Phase 2 spread across the Roe Farms land. A third effort sampled deep soil. This study looked wider: uranium isotopes plus americium, plutonium and technetium-99, and, in Phase 2, lead, mercury, petroleum hydrocarbons, 21 pesticides and asbestos.
Its findings: americium, plutonium and technetium-99 were not detected in the Phase 1 samples. Several U-238 results ran numerically above the PORTS surface-soil background figure of 1.36 picocuries per gram — the highest, at Sample #12, was 2.00 — but the report retained a “PASS” for them because the laboratory uncertainty overlapped the background values. Phase 2 found low-level americium and plutonium below screening levels and no technetium-99. Lead and mercury were below comparison values, all 21 pesticides were not detected in surface or deep samples, and asbestos was not detected. The report’s overall conclusion is that the sampled soils “do not exhibit a site-related contamination condition,” and that the uranium is “most reasonably attributed to naturally occurring background.”

What the fine print says
Three things about those clean bills of health are in the documents themselves.
First, both studies were commissioned by the developer as due diligence for land it is evaluating or has bought — and both are stamped “Confidential Business Information.” They are nonetheless sitting in Ohio EPA’s public document portal, where anyone can read them.
Second, the QAL-TEK report states in its own introduction that “SB Energy selected the Phase 2 sample population” — the developer chose which samples made up the broader study, with a software tool used to spread the locations out.
Third, the reports carry their own limits. Stantec’s letter states that it “cannot represent that the Site does not contain any hazardous or toxic materials or other latent conditions beyond that observed.” QAL-TEK notes that some of its U-235 detection limits sat above the screening value — meaning at those spots, the test could not have seen contamination at the screening level if it was there. And the highest uranium reading in the whole package passed not because it was below background, but because the measurement’s margin of error was wide enough to cover background.
None of that makes the soil dirty. It means the word “clean” in this file rests on the developer’s own consultants, the developer’s own sample selection, and uncertainty math — a distinction the people who live downwind have learned to watch closely.
The monitors: the government now needs the developer’s permission
The second letter may matter more in the long run.
On November 24, 2026, the Department of Energy’s Portsmouth/Paducah Project Office wrote to Karl Brutsaert, vice president of Pike County Portsmouth DC LLC — the data center company, at the same Redwood City, California address as SB Energy. DOE explained that it runs environmental monitoring at off-site locations around the old plant: ambient air monitors and groundwater wells that “evaluate potential impacts from DOE activities.” The Ohio Department of Health runs its own air monitors at the same spots, independently. DOE’s contractors and state health staff visit these stations regularly to collect samples and maintain equipment, under real-estate license agreements that expire and must be renewed.

DOE had been renewing one of those licenses with Nathan Ewing of ROE Farms, LLC — covering an air monitoring station, six groundwater wells and other sampling on two parcels, 20-048000 and 20-48500. Then, DOE wrote, it learned the parcels “have been purchased by PORTS DC.”
So the federal government is now asking the data center developer for a license to keep monitoring. If a license “cannot be established,” DOE wrote, it “will need to remove all its equipment, fixtures, appurtenances, and other improvements” from the land — or, if the developer prefers, abandon the equipment in place.
And it may not stop at those two parcels. “DOE believes that there are other properties with existing license agreements that were purchased by PORTS DC,” the letter says, asking to resolve monitoring access at those locations too.

Read the two letters together and the shape of the new Piketon is hard to miss. The state is warning that pumping could move the old plant’s poisons. The developer is promising not to pump, and offering its own testing as proof the ground is fine. And the public’s independent window into what comes off that plant — the air monitors and wells that have watched PORTS for decades — now sits, in part, on the developer’s land, kept or removed at the outcome of a private negotiation the public is not part of.
The digging already mapped
The permit file also holds the project’s geotechnical investigation maps for Permit Area 1 — the grid of borings and test pits around Bobo Road, Dutch Run Road and Little Beaver Creek where engineers are already probing the ground the campus will stand on. The permit’s own conditions show the care the contamination next door demands: all work kept outside a 50-foot buffer around streams and water features, drill cuttings and excavated soil barred from entering creeks, wetlands and drainage ways, and soil not to be trucked across the site from boring to boring.

The 401 certification — Ohio EPA ID No. 262779A2 — remains in the agency’s process, with the developer’s answers now on the record. The monitoring-license negotiation between DOE and PORTS DC is, as of the November 24 letter, awaiting the developer’s response.
The documents
Every document cited in this story is published in full here, exactly as it sits in Ohio EPA’s public portal:
- Ohio EPA’s 401 comments and Portsmouth DevCo’s responses — November 23, 2026 (the plume warning, the water answer, the soil answer).
- DOE’s monitoring-license letter to Pike County Portsmouth DC LLC — November 24, 2026 (the air station, the six wells, the other properties).
- Stantec, Summary of Soil Assessment Activities — April 10, 2026 (15 locations, uranium).
- QAL-TEK, Soil Sample Characterization Final Report — August 16, 2026 (59 pages; Oklo property, Roe Farms, deep soil).
- PORTS Project Area Permit 1 — Geotech Investigation maps (boring grid, crossings, buffer conditions).