WAVERLY, Ohio — The Pike County Board of Commissioners will hold a special meeting on Tuesday, Nov. 24, at 6:30 p.m. to receive public comment on the non-binding term sheet for the proposed PORTS Technology Campus, the artificial intelligence data center project SB Energy wants to build at and around the former Portsmouth Gaseous Diffusion Plant in Piketon.
The order of those two events is the story. The board approved the term sheet on Nov. 18, by Resolution No. 1011-26. The public comment session comes six days after the approval. The board says it does not expect to take formal action at the Nov. 24 meeting.
The meeting is in the Conference Room of the Pike County Government Center, 230 Waverly Plaza, Suite 104, in Waverly, under notice given pursuant to Ohio Revised Code Sections 121.22(F) and 305.07. Speakers are asked to limit remarks to three minutes.
What the document says
The five-page Summary of Principal Terms — published in full at the bottom of this story, in photographs of the document provided by Pam Cutler Ison — describes a campus of up to 17 data center buildings on several thousand acres, with OpenAI as the tenant. It estimates about 2,500 full-time permanent jobs at full build-out, at an average annual salary of approximately $110,000, with construction expected to begin in 2026.
The money, on paper:
- Payments in lieu of taxes (PILOT): $1.5 billion over 15 years — paid, the document says, in exchange for a 15-year, 100% real property tax exemption for each building. The $1.5 billion assumes all 17 buildings are built; if fewer are built, the annual payments are owed only for buildings actually built.
- Upfront capital investment: $300 million — triggered, the document says, if a new Pike County port authority approves a 100% sales and use tax exemption for construction materials.
- Local sales and use tax guarantee: $1.5 billion to $2.25 billion over 15 years.
- Total package at full build-out of 17 buildings: $3,306,000,000 to $4,056,000,000.
- The Pike 2040 Community Foundation commitment is listed as TBD — the document states it is “for discussion purposes only and has not been agreed to.”
The document’s own footer states what the commissioners’ notice also states: the summary “is provided for informational purposes only and is not binding.” Any final development agreement must be negotiated and considered separately by the board at a future public meeting.

The record
J News Network’s reporting on the Nov. 18 meeting — “Finalized at 1:30 a.m., approved the same day” — documented that the term sheet was finalized in the early-morning hours and approved by the board the same day. The public comment session follows the approval by six days. Figures presented at that meeting ran as high as $3.6 billion to $4 billion; the county’s own release said $3.3 billion. The document itself, published below, states $3,306,000,000 to $4,056,000,000 — at full build-out of all 17 buildings, a condition attached to every headline number in it.
The $105 billion figure attached to this project in state and national announcements is not in this document and is not project spending: it is a credit-support guarantee cap behind SB Energy and OpenAI that pays only in the event of a default, and nothing has been paid under it. That record is laid out in JNN’s earlier reporting here.
How to comment
Members of the public may comment in person at the meeting. Written comments may also be submitted to the Clerk of the Board, Julia Day, at 230 Waverly Plaza, Suite 1000, Waverly, Ohio 45690, or by email to ports-pikeinfo@pikecounty.oh.gov, through the close of the meeting on Nov. 24.
Copies of the term sheet are available for review at the Board of Commissioners office, 230 Waverly Plaza, Suite 1000, Waverly, during regular business hours, and on the commissioners’ website at www.pikecountyohcommissioners.gov.
The term sheet, in full
The complete five-page Summary of Principal Terms (document 4912-7067-3122, v. 2), photographed and provided to J News Network by Pam Cutler Ison: