Cranes set beams for 700-foot Pratts Fork Creek bridge in Athens County

Advertisement

ATHENS COUNTY, Ohio — Cranes are setting the prestressed concrete beams for the new eastbound U.S. 33 bridge over Pratts Fork Creek in Athens County, part of the Ohio Department of Transportation’s $274 million expansion of the highway through southeastern Ohio.

Video posted by ODOT District 10 shows two cranes swinging one of the bridge’s massive concrete I-beams into place above the creek valley while crews guide it from the deck and an oversize-load trailer waits on the existing roadway.

Advertisement
Advertisement
CapCut
Cranes set prestressed concrete beams for the new eastbound U.S. 33 bridge over Pratts Fork Creek in Athens County. (Ohio Department of Transportation District 10)

The eastbound U.S. 33 structure over Pratts Fork Creek is a five-span prestressed concrete I-beam bridge more than 700 feet long and about 80 feet high, Blake Brown, area engineer for ODOT District 10, said in the department’s September 2026 project update, as reported in trade coverage of the project. Brown pointed to the Pratts Fork Creek bridge as one of the most important aspects of the project.

Advertisement
TDY Rentals — Furnished homes for TDY stays

The bridge is one of six being built in Athens County under the expansion, which converts 25 miles of U.S. 33 in Athens and Meigs counties from two lanes to a four-lane divided highway — the last two-lane segments of the route between Columbus and the Ohio River, according to the Columbus Dispatch. Kokosing Construction Company Inc. submitted the low bid on all four of the project’s contracts and is building the entire program.

Advertisement
Southwest Airlines Rapid Rewards

In Athens County, crews who started work in fall 2025 are excavating about 4 million cubic yards of earth for 10 miles of new eastbound roadway, three mainline bridges and three overpasses. The Athens-to-Darwin section, 10.78 miles, adds grade-separated interchanges at Pleasant Hill Road, Pleasanton Road, Rainbow Lake Road and State Route 681, and the existing U.S. 33 pavement becomes the other half of the divided highway after resurfacing and tie-in work.

Advertisement

ODOT expects the new alignments to open by the end of 2027, followed by final resurfacing, grading and related work through fall 2028. “The Athens corridor is still on schedule to complete by fall 2028,” Brown said.

Truck traffic makes up a large portion of the vehicles on U.S. 33 from Athens to West Virginia, and the expansion will stop cars from having to pass trucks on a two-lane road and risk a head-on crash, Ashley Rittenhouse, ODOT District 10 public information officer, told the Dispatch.

This story is based on ODOT District 10’s posted video and project statements, the department’s September 2026 project update, and Columbus Dispatch reporting on the expansion.