A nuclear power developer is offering a Brown County landowner $335,000 an acre for property it calls a potential site for “long-term energy infrastructure,” according to a letter mailed to the landowner on Blue Energy letterhead.
The letter says Blue Energy “has identified properties that you own in Brown County, Ohio, as a potential site for long-term energy infrastructure,” that the company is “exploring the possibility of purchasing properties for our project,” and that it is “offering a purchase price of $335,000/acre.”

The letter describes Blue Energy as “a U.S.-based energy developer of modern, modular nuclear power plants,” and pitches small modular reactors on their passive safety features, smaller footprints and standardized, factory-fabricated designs.
The letter is not the only one mailed in the county. Another Brown County resident posted a photograph of the same letter publicly on Nov. 5.
For scale, the U.S. Department of Agriculture put Ohio cropland at an average value of $10,100 an acre in 2026. The figure in the letter is more than 33 times that average.
Blue Energy, legally Blue Energy Global Inc., was founded in 2023 as a spinout of the Massachusetts Institute of Technology’s nuclear science and engineering department and is headquartered in Chevy Chase, Maryland. The company raised $45 million in its 2024 launch round and a further $380 million in April 2026, and in July 2026 it announced a strategic investment from Constellation Technology Ventures, the venture arm of Constellation Energy.
The company’s only announced project is in Texas: a 2.5-gigawatt plant planned at the Port of Victoria that would pair gas turbines with up to five GE Vernova Hitachi BWRX-300 small modular reactors to power a data center campus. In September 2026 the company filed the first part of a phased construction permit application with the U.S. Nuclear Regulatory Commission; the filing is in acceptance review and no permit has been issued.
Blue Energy says its plants are prefabricated as modules in shipyards and delivered to sites by barge. Brown County fronts the Ohio River at Ripley and Aberdeen. The company has announced no project in Ohio.
Blue Energy is the second reactor developer to surface in Brown County this year. On April 13, 2026, Geenex Power, a Charlotte, North Carolina developer, presented the Brown County commissioners a proposal for a 300-megawatt small modular reactor campus between Ripley and Aberdeen, a project it valued at $1.2 billion to $1.8 billion and said it already held land control for. The two companies are separate, and Geenex’s proposal is the only one that has been presented to the county publicly.
Any reactor built in Ohio would need a construction permit from the Nuclear Regulatory Commission and a certificate from the Ohio Power Siting Board. No application by Blue Energy for an Ohio site appears in either agency’s public records.